
The station's constructions include the dam, a power plant building located near the dam, and an
additional spillway which is under construction. The arch-gravity dam is 242 metres high. It has a
crest length of 1,066 metres, crest width of 25 metres, base width of 105.7 metres and maximum head
of 220 metres. It consists of a solid left-bank dam 246.1 metres long, a power dam 331.8 metres long,
a spillway dam 189.6 metres long and a solid right-bank dam 298.5 metres long. It is by far the larger
of only two gravity-arch dams in Russia. Water pressure for the dam is approximately 30 million tons,
of which 60% is neutralized by the dam's own weight and 40% is carried to rock on the bank.
The dam supports the Sayano-Shushenskoe reservoir, with a total capacity of 31.34 km3, useful capacity
of 15.34 km3 and surface area of 621 km2.
The dam is constructed to "safely" withstand earthquakes up to 8 on the Richter scale, and
was recorded by the Guinness Book of World Records for the strongest construction of its type.

The station is the largest one contributing to peak consumption in the Unified Energy Systems of
Russia. More than 70% of generated electrical power goes to Rusal's four smelters in Siberia.
In years of heavy rainfall, about 1,600-2,000 GWh are lost due to lack of high-voltage line transmission
capacity, and some water bypasses the turbines. To avert this, a new aluminium plant was started on
15 December 2006.
The decision to build the power station was taken in 1960. On 4 November 1961, geologists reached
the area, and an exact location was chosen. Construction started in 1963 and the first turbine went
online on December 18, 1978. Plant became fully operational in December 1985. It was partially reconstructed
in 1987 and in 1991. The plant was designed by the Leningrad (now Saint Petersburg) branch of the Hydroproject
institute, Lenhydroproject.
Following the collapse of the Soviet Union, the power plant was privatized in 1993, with RAO UES becoming
the main shareholder. In April 2003, the Government of Khakassia by the initiative of the governor
Alexei Lebed filed a suit to invalidate the deal. In April 2004, the East Siberian Arbitration invalidated
the deal; however, it was overruled by the Supreme Arbitration Court.
The plant was closed after an accident on 17 August 2009. Some of the old turbines were subsequently
restarted temporarily, but all are being sequentially replaced with updated more efficient equipment.
As of Nov. 2014, all 10 generators are operational.

On 17 August 2009 at 8:13 AM, the hydro-electric plant suffered a catastrophic accident that caused
flooding of the engine and turbine rooms, and two 711 MVA electric generators to explode underwater
as a result of a short circuit. All other machinery was damaged to some extent, with only four hydro-aggregates
ultimately recoverable; the remaining six required replacement. As of 10 September 2012, 75 people,
including 1 pregnant woman, were confirmed dead, while one person was still listed as missing forty
days after the disaster.
Power generation from the station ceased completely following the incident, with the resulting blackout
in residential areas being alleviated by diverting power from other plants. Aluminium smelters in Sayanogorsk
and Khakassia were completely cut off from the grid before power supplies were replaced using alternate
power source. Russia warned that in the longer term it might lose up to 500,000 tons of aluminum output
due to the power shortage, and called for accelerating the construction of the Boguchanskaya hydroelectric
power station to replace lost generating capacity.
The accident caused an oil spill with at least 40 tonnes of transformer oil released, spreading over
80 km downstream of Yenisei.
The plant restarted operations on 24 February 2010, while repairs were complete by November 2014. According
to Russian Energy Minister Sergei Shmatko the rebuilding of the engine room alone would cost $1.2
billion.
Dam subcontractor Gidroelectroremont's chief accountant has been accused by the Khakassia police of
embezzling 24 million rubles from the funds allocated by RusHydro for repairing the dam.




