Non Destructive Testing

Hydrostatic testing of pressure piping systems in practice

Hydrostatic testing of pressure piping is a mandatory activity before finalization of any new or modified piping system. It is the final check of mechanical integrity of the whole system and should be followed religiously as after this activity the piping system has to be commissioned. This test is carried out at a pressure 1.5 times higher than the design pressure of a system regardless of the service conditions of a piping system. This article discuss some of the major requirements of hydrostatic testing of pressure piping as per ASME B31.3 for process piping and specifically provides guidelines on some issues not directly addressed in the code.

Some guidlines

Preparation and Testing

  1. Pressure gauges should be fitted at both low and high point when testing large volume systems.
  2. The system shall be filled from the lowest available point; all vents and high point connections shall be open during this operation to allow the air in the system to vent off.
  3. After the system has been completely vented all vents and drains should be plugged or blinded. Verify that Valves are in place and open/closed as required.
  4. Maintain pressure for 10 minutes and then gradually increase pressure in steps of one tenth of the test pressure until the test pressure is attained. The recommended practice of a QC inspector is to walk through the whole piping system and check for leaks. Every single length of piping, welds, bolted connections shall be visually examined for any leakage. Duration of this activity varies with the span of piping system. For larger piping system time taken for this activity is enough to clear the hydrostatic test. In case of piping system having smaller span, 1 hour time may be made as standard practice.
  5. Whenever a leak is found from flanged connection, it is advisable not to perform any tightening before the system pressure is brought down to at least 70%. A leak from a weld joint, piping base metal or any other location which may require hot work shall only be addressed after de-pressurizing the piping under test.
  6. After any leaks have been repaired the system shall again be pressurised to the test pressure in stages.
  7. The test should be witnessed and accepted by a third party, client representative or a responsible person within the company and signed as accepted.
  8. Pressure and ambient temperatures should be recorded throughout the complete test cycle. These charts should form part of the Hydrostatic Test Documentation.
  9. On completion of the test, the system shall be depressurised by controlled means and all vents opened prior to draining of the system to avoid any vacuum within the system.

to be continued...